Mechanic's lien · Los Angeles, CA
Mechanic's lien in Los Angeles, CA
In Los Angeles, contractors must serve a Preliminary Notice within 20 days of first furnishing labor or materials (Civ. Code § 8800) to preserve mechanic's lien rights. The notice must be sent to the property owner and construction lender via certified mail.
Governing statutes
90
days to record a claim of lien (Civ. Code § 8412)
90
days to sue on a recorded lien (Civ. Code § 8460)
$24.99
one-off, preview free
The process in Los Angeles
- 1
Serve Preliminary Notice
Within 20 days of first furnishing labor or materials, serve a Preliminary Notice per Civ. Code § 8800(f). Send via certified mail to the owner, general contractor, and construction lender.
Civ. Code § 8800(f)
- 2
Record Mechanic's Lien
If unpaid, record a Mechanic's Lien with the LA County Recorder within 90 days of completion or 60 days after notice of completion, whichever is earlier (Civ. Code § 8410).
Civ. Code § 8410
- 3
File Lien Foreclosure
File a lawsuit to foreclose the mechanic's lien within 90 days of recording. The LA County Superior Court handles lien foreclosure cases.
Los Angeles filing details
2-3 weeks for case assignment · Filing fee: $240–$435 depending on the amount demanded
LA County Recorder processes mechanic's lien recordings within 5-7 business days.
Preliminary notice requirements are strictly enforced in California — missing the 20-day deadline forfeits lien rights for work performed before the notice.
Los Angeles Superior Court filing fee for a lien foreclosure (Statewide Civil Fee Schedule, effective January 1, 2026): $240 if the amount demanded is $10,000 or less; $385 if it is over $10,000 up to $35,000; $435 if it is over $35,000. Confirm the current fee with the clerk before filing.
Where a lien is recorded
LA County Registrar-Recorder / County Clerk
12400 Imperial Hwy, Norwalk, CA 90650
Where it is filed
Los Angeles Superior Court — Stanley Mosk Courthouse
111 N Hill St, Los Angeles, CA 90012
Documents on this track
Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.
- Preliminary NoticeCiv. § 8800(f)
- Mechanic's LienCiv. § 8400
- Demand LetterPre-lien demand
Read the governing statute
Questions people ask about Los Angeles
What is the deadline for preliminary notice in LA?+
Contractors must serve a Preliminary Notice within 20 days of first furnishing labor or materials (Civ. Code § 8800). Missing this deadline forfeits lien rights for all work performed before the late notice is served.
How much does it cost to file a mechanic's lien in LA County?+
Recording fees at the LA County Recorder are approximately $14 for the first page and $3 per additional page. A foreclosure lawsuit is a civil action, so the LA Superior Court filing fee follows the amount demanded (Statewide Civil Fee Schedule, effective January 1, 2026): $240 up to $10,000; $385 over $10,000 up to $35,000; $435 over $35,000. Confirm the current fee with the clerk before filing.
Does a recorded Notice of Completion shorten my California lien deadline?+
Yes, sharply. A direct contractor gets 60 days after a notice of completion or cessation is recorded, and other claimants get 30 days (Civ. Code § 8412/8414). With no notice recorded, the outside date is 90 days after completion of the work of improvement. The owner controls when that clock starts, so check the recorder before you calendar anything.
When must a California mechanic's lien be recorded?+
Within 90 days after completion of the work of improvement, or 30 days after a notice of completion or cessation is recorded (Civ. Code § 8412). Direct contractors are measured differently from subcontractors, so confirm your tier before you calendar the date.
How long does a recorded California lien stay alive?+
Ninety days. You must file the foreclosure action within 90 days of recording unless you record a valid extension based on the owner's written agreement (Civ. Code § 8460). Recording is not collection — the 90-day clock starts the afternoon you record.
What is a stop payment notice and do I still need it?+
A stop payment notice under Civ. Code § 8500 et seq. reaches construction funds still in the owner's or lender's hands, which is a different pot from the property itself. It does not replace the 90-day recording window, and on many private jobs it needs a stop-notice bond. Most claimants still need preliminary-notice compliance first.
Does a recorded Notice of Completion shorten my California lien deadline?+
Yes, sharply. A direct contractor gets 60 days after a notice of completion or cessation is recorded, and other claimants get 30 days (Civ. Code § 8412/8414). With no notice recorded, the outside date is 90 days after completion of the work of improvement. The owner controls when that clock starts, so check the recorder before you calendar anything.
Also in this jurisdiction: Eviction notice (Los Angeles) · Eviction notice (San Diego)
Generate Your LA Preliminary Notice
EvictFlows generates Civ. Code § 8800-compliant preliminary notices for Los Angeles contractors. Free preview, certified mail ready.