Contractor deadline tool

20-day preliminary notice calculator

Civil Code § 8204 gives you 20 calendar days from first furnishing to serve the preliminary notice; § 8200 sets who must give it and who receives it. Enter that first date and the tool returns the deadline, tells you whether you are still inside the window, and quantifies what a late notice costs.

Statutes behind this calculation

Cal. Civ. Code § 8200Cal. Civ. Code § 8202Cal. Civ. Code § 8204Cal. Civ. Code §§ 7, 10

20

calendar days from first furnishing

Civ. Code § 8204

Day 20

deadline for subcontractors, suppliers and equipment lessors

not the invoice date

20 days

of work that survives a late notice

§ 8204 late-service penalty

Find your 20-day deadline

The count starts the day after the trigger date for your role: first furnishing for a subcontractor, supplier or equipment lessor; commencement of the work of improvement for a design professional (Civ. Code § 8204(b)). Day 20 is the deadline.

The first day you or your crew were on site, or the first delivery. This is day 0 — it is not counted.

Serve the owner, the direct contractor, and the construction lender if the lender recorded a notice of construction loan or asked to be notified.

Serve the owner, the direct contractor if you were hired by someone else, and any construction lender that recorded a notice of construction loan or asked to be notified (Civ. Code § 8200(a)).

Who receives the notice

  • · Owner or reputed owner
  • · Direct contractor, if you were hired by someone else
  • · Construction lender, if one is on the project

Day 0 — first furnishing

Tue, Nov 24

not counted

Preliminary notice deadline

Mon, Dec 14, 2026

Day 20 — serve on or before this date

You have 20 days left. Serve now — the notice protects work from here forward, not the work you already finished.

Serve it before anything else

The notice does not depend on nonpayment. Send it inside the first 20 days, keep the proof of service, and calendar the lien-recording deadline now — typically 90 days after completion under Civil Code § 8412, then 90 days to enforce after recording.

Free preview first. The date you entered is carried into the draft.

How the 20 days are counted

The window is short, and the arithmetic is not the one most contractors assume.

  • The clock starts at first furnishing — not at the first invoice and not at completion. On a job that ran for months, the 20 days were gone long before anyone noticed the bill was unpaid. A design professional is the exception: § 8204(b) starts the clock at commencement of the work of improvement, not at the first day of design work.
  • It is 20 calendar days, not 20 business days. Civil Code § 10 excludes day 0 and includes the last day; weekends inside the window still count.
  • The notice goes to the owner, the direct contractor if you were hired by someone else, and the construction lender if it recorded a notice of construction loan or asked to be notified. A direct contractor serves the lender only, and a laborer serves no one.
  • The notice is not a lien and not a lawsuit. It is the announcement that keeps the lien available if the invoice goes unpaid.

What a late notice actually costs

Missing the date is not fatal — it is expensive, and the price is measured in work, not paperwork.

  • § 8204 limits a late notice to work furnished in the 20 days before it was served. Everything earlier drops out of the lien.
  • The earlier work is still owed under the contract, and you can sue on the contract. What you lose is the recording remedy that attaches to the property.
  • On a job that started months before the invoice, that 20-day slice can be most of the claim.
  • A notice served on time is also cheaper to defend: the lien amount and the dates line up with the notice already in the file.

What to send next

Three steps, in this order.

  1. 1

    Serve the preliminary notice

    Owner, direct contractor, and the lender if one is on the project. The content is prescribed by Civil Code § 8202, including the statutory warning language.

  2. 2

    Keep the proof of service

    Method, date, recipient, and address for each copy. The declaration is what proves the notice went out when you say it did.

  3. 3

    Calendar the lien deadline

    Recording is typically due 90 days after completion under Civil Code § 8412, and the suit to enforce is due 90 days after recording under § 8460. Put both dates in the file now.

Where this fits

20-day preliminary notice questions

Is the 20-day preliminary notice deadline 20 business days or 20 calendar days?+

20 calendar days. Civil Code § 10 excludes day 0 — the first furnishing date — and includes day 20. Weekends and holidays inside the window still count. Only a deadline that lands on a weekend or state holiday rolls to the next business day under Civil Code §§ 7 and 10, and you should not plan around that.

What happens if I serve the preliminary notice after 20 days?+

It still works, but only for work furnished in the 20 days before it was served. Earlier work is no longer lienable, though it remains collectible under the contract.

Do I need a preliminary notice if I have a direct contract with the owner?+

A direct contractor has a narrower duty than a subcontractor. Under Civil Code § 8200(e)(2), a direct contractor gives the preliminary notice only to the construction lender, and if no lender is on the project, no preliminary notice is required to preserve its lien rights. Laborers are exempt entirely under § 8200(e)(1). Select your role in the calculator so the recipient note matches your position.

Who has to receive the preliminary notice?+

The owner and the direct contractor, plus the construction lender if it recorded a notice of construction loan or asked to be notified. On an owner-occupied dwelling of four units or fewer, the lender copy is generally not required.

Does the notice protect work I already finished?+

No — it protects the lien from the point it is served forward, which is exactly why the deadline matters. Work furnished before a late notice survives only if it falls inside the 20-day lookback.

Is there another deadline after the preliminary notice?+

Yes. Recording is typically due 90 days after completion under Civil Code § 8412, and the enforcement suit is due 90 days after recording under § 8460. Missing either one ends the lien.

Turn the 20 days into a served notice

Generate the § 8202-compliant preliminary notice with your first-furnishing date already filled in. Free preview, PDF with the proof of service attached.

Landlord? Use the California 3-day notice calculator →

Free preview before you pay. Every notice cites the statute it was built from.

EvictFlows is document-generation software, not a law firm, and does not give legal advice. This calculator counts days; it does not decide whether your project is covered by Civil Code § 8200.