Civil Code 8200: the construction notice to owner that protects your lien

Civil Code § 8200 requires a claimant without a direct contract with the owner — typically a subcontractor, material supplier, equipment lessor, or design professional — to give the owner a preliminary notice. Section 8204 requires the notice within 20 days after first furnishing labor or materials to the project. The notice is also given to the direct contractor, and to the construction lender on request. Serve it late and the lien is limited to work furnished in the 20 days before the notice was given; skip it entirely and there is generally no lien at all.

Citations on this page

Cal. Civ. Code § 8200Civ. Code § 8204Civ. Code § 8412Civ. Code § 8460

Last checked against the code: 2026-11-01

20

days

Window to give preliminary notice after first furnishing

Civ. Code § 8204

90

days

Typical window to record the lien after completion

Civ. Code § 8412

90

days

Time to enforce a recorded lien

Civ. Code § 8460

Civil Code 8200, in plain English

Read the section the way a court reads it — what it does, what it requires of you, and where filings usually fail.

What the notice is for

The owner has a right to know who is working on the property and who may later record a lien. The preliminary notice — commonly called a construction notice to owner, a 20-day notice, or a pre-lien notice — is how a claimant without a direct contract announces itself.

It is not a lien. It is not a lawsuit. It is a statutory warning that preserves the right to record a lien later if the invoice goes unpaid.

Who has to give it

Any claimant who does not have a direct contractual relationship with the owner: subcontractors at every tier, material suppliers, equipment lessors, and design professionals. Laborers are exempt.

A direct contractor has a narrower duty: under Civil Code § 8200(e)(2) it gives the preliminary notice only to the construction lender, and if no lender is on the project, no preliminary notice is required to preserve its lien rights. Laborers are exempt under § 8200(e)(1).

Who receives it

The owner, and the direct contractor if the claimant was hired by someone other than the direct contractor. If the project has a construction lender and the lender has requested notice, the lender is served as well.

The address matters. Send it to the owner's address as stated in the building permit or recorded construction contract where the statute allows reliance on those records.

The 20-day window and the late penalty

Civil Code § 8204 sets the window: it runs from the first furnishing of work, not from the invoice date and not from completion. Twenty days is short: on many jobs the first delivery happens before the paperwork is organized.

A late notice is not fatal, but it is expensive. Under § 8204 the lien is generally limited to the work furnished in the 20 days immediately before the notice was given. On a job that started months earlier, that can erase most of the claim.

What the notice must contain

Civil Code § 8202 prescribes the content: the claimant's name and address, the owner's name and address, the direct contractor's name and address, a general description of the work, and the estimated total price of the work.

The statute also prescribes language warning the owner about lien liability. Omitting that language is a defect, not a stylistic choice.

Proof it went out

Proof of service should be completed at the time of service — method, date, recipient, and address. The declaration is what converts a stack of paper into evidence that a lien is still alive.

What actually has to be right

  • 20 days from first furnishing under Civ. Code § 8204 — not from the invoice or completion.
  • Subcontractors, suppliers, and equipment lessors generally need it; laborers do not.
  • Serve the owner, the direct contractor, and the lender on request.
  • A late notice limits the lien to the 20 days before service under § 8204.
  • § 8202 prescribes both the content and the statutory warning language.

How to serve the preliminary notice

The statute allows personal delivery, first-class mail, certified or registered mail, or overnight delivery, with the method recorded on the proof of service.

  1. 1

    Send it early

    Serve inside the first 20 days of furnishing. Do not wait for the first unpaid invoice — the notice protects future work, not past work.

  2. 2

    Serve every required party

    Owner, direct contractor, and any construction lender that requested notice. Missing a required recipient narrows what the lien can reach.

  3. 3

    Keep the proof

    A completed proof of service for each recipient, retained with the project file, is what you produce if the lien is challenged.

Cal. Civ. Code § 8200

Generate a 20-day preliminary notice cited to Civil Code 8200

Answer a few facts, preview the full document free, then unlock the court-ready PDF and proof-of-service packet. Every draft prints the section it relied on.

  • 20-Day Preliminary NoticeCiv. Code §§ 8200, 8202, 8204
  • Mechanic's LienCiv. Code § 8412

Filing this in a specific city

Local venue, recorder, and county deadlines for the same document.

Civil Code 8200 questions

Is the construction notice to owner the same as a preliminary notice?+

Yes. Contractors commonly say “construction notice to owner,” “20-day notice,” or “pre-lien notice.” The statutory name is the preliminary notice under Civil Code § 8200.

What happens if I miss the 20 days?+

The notice can still be given, but the lien is generally limited to labor and materials furnished in the 20 days before it was served. Anything earlier can drop out of the claim.

Do I need to send it if I have a direct contract with the owner?+

A direct contractor gives the preliminary notice only to the construction lender. If no lender is on the project, no preliminary notice is required to preserve its lien rights under Civil Code § 8200(e)(2). Laborers are exempt entirely under § 8200(e)(1).

Does a preliminary notice expire?+

It covers the work of improvement it was given for. A separate, later project generally needs its own notice.

Do I also have a deadline to record the lien?+

Yes — typically 90 days after completion under Civil Code § 8412, then 90 days to enforce after recording under § 8460.