What a preliminary notice does
A preliminary notice (sometimes called a pre-lien notice, notice to owner, or 20-day notice depending on the state) is a written document sent to the property owner and other interested parties early in a construction project. Its purpose is to preserve your right to later record a mechanic's lien if you are not paid. Without it, the lien may be invalid — and without a valid lien, you are an unsecured creditor chasing an invoice.
Deadline comparison across 11 states
California: 20 days after first furnishing (Civ. Code § 8800). Texas: the 15th day of the second month after each month worked (Prop. Code § 53.056). Florida: 45 days after first furnishing (§ 713.06). New York: no statutory preliminary notice for private projects, but a notice of intent is common practice. Washington: 10 days after first furnishing for those not in direct contract with the owner (RCW 60.04.031). Arizona: 20 days after first furnishing (A.R.S. § 33-992.01). Illinois: 60 days after first furnishing for subcontractors (770 ILCS 60/5). Colorado: a notice of intent to lien must be served before recording (C.R.S. § 38-22-109). Georgia: no preliminary notice required for direct contractors; subcontractors must send within 30 days. North Carolina: no preliminary notice for most private projects. Nevada: 31 days after first furnishing (NRS 108.226).
What happens when you miss the deadline
Missing the preliminary notice deadline does not always destroy the entire claim. In most states, it destroys the claim for work furnished before the notice was sent — but work furnished after a timely notice remains protected. This is why sending the notice early and sending it monthly (where required) matters: each late month is a month of revenue you can no longer lien.
Sending to the right parties
Every state specifies who must receive the preliminary notice. Common recipients are the property owner, the original (general) contractor, and the construction lender. Sending to the wrong person — for example, sending to the builder's holding company instead of the record owner — is the same as not sending at all. EvictFlows populates the correct recipients based on the state and your role in the project.
Frequently asked questions
+What is a preliminary notice deadline?
The last day you can send a preliminary notice and still preserve your lien rights for work furnished in a given period. It varies by state — California is 20 days, Texas is the 15th of the second month after, Florida is 45 days.
+What happens if I miss the deadline?
You typically lose the right to claim a lien for work furnished before the late notice. Work furnished after a timely notice may still be protected.
+Do I need a preliminary notice in every state?
No. Some states do not require one for direct contractors, and a few do not require one at all for private projects. But even where not required, sending one is best practice.
+Can EvictFlows generate preliminary notices for all 11 states?
Yes. EvictFlows generates state-compliant preliminary notices with the correct recipients, deadlines, and statutory language — free preview, court-ready PDF.