Recording is step two, not the finish
Civil Code § 8400 lets you record a claim against the property you improved. That recording is a deadline machine, not a check. Under § 8460, you generally must commence an action to foreclose the lien within 90 days after recording. Miss it and the lien is unenforceable without a new, timely claim — which you usually no longer have.
Extensions are narrow
Section 8461 allows a recorded extension if the claimant and owner agree in writing. Do not assume a handshake or an open invoice extends the statute. If you are still negotiating, get the extension recorded before day 90, or file the foreclosure and keep talking.
Match the lawsuit to the lien
The foreclosure complaint should track the recorded claim: owner of record, legal description or APN, work description, and amount after credits. Inflating the number, suing the tenant instead of the owner, or describing a different building are how expungement motions succeed.
Bonds and releases
An owner or lender may bond around the lien. A recorded release after payment should be part of the closeout, not an afterthought. Generate the lien while the completion date is still in the file, then put the 90-day suit date on the same calendar.
Frequently asked questions
+Does recording the lien get me paid?
No. Recording preserves a claim against the property. Collection still requires payment, a settlement, a bond, or a timely foreclosure action under Civil Code § 8460.
+Can I extend the 90 days by sending another invoice?
No. An extension generally requires a written agreement with the owner that is recorded. An unpaid invoice does not stop the clock.
+What if I recorded in the wrong county?
The lien belongs in the county where the improved property sits. A recording in the wrong county does not start a valid 90-day enforcement period on the parcel you actually worked.