The 20-day preliminary notice under § 8800 tells the owner and lender you are on the job. The demand letter asks to be paid. The mechanic's lien under § 8400 is recorded against the property. Mixing the captions, or treating the demand as if it were the prelim, is how claimants miss a statutory step they thought they had already taken.
What belongs in the letter
Identify the property, the contract or invoices, labor and materials actually furnished, payments and credits, and a date to pay. A good-faith number matters later if you record. Threats that you will lien a neighboring parcel, or inflate extras you cannot document, create the expungement record you do not want.
It does not buy time
Owners sometimes ask you to 'wait on the letter' through the recording deadline. The Code does not pause because you were polite. If completion is close, send the demand and prepare the lien in the same sitting. You can release a recorded claim after they pay. You cannot revive an unrecorded claim after the window closes.
Then record, or don't
If they pay, send a written confirmation and keep the unrecorded draft. If they do not, record in the county of the job and serve as the Code requires. The 90-day foreclosure clock under § 8460 starts on recording, not on the demand letter's date.
Frequently asked questions
+Is a demand letter required before a California mechanic's lien?
No. The Civil Code does not make a demand letter a condition of recording. It is still often the cheapest way to get paid if you send it while the recording clock is open.
+Can the demand letter replace the 20-day preliminary notice?
No. Preliminary notice under § 8800 is a separate statutory step for most claimants who did not contract with the owner. A payment demand does not satisfy it.
+Does sending a demand extend the time to record?
No. The time to record is measured from completion or a notice of completion, not from your letter. Calendar the statutory date independently.