Step 1: Confirm your right to lien
Not everyone who is owed money on a construction project has lien rights. In most states, direct contractors, subcontractors, and material suppliers can claim a lien. Some states extend rights to design professionals and equipment lessors. Check your state's statute to confirm your tier of claimant qualifies.
Step 2: Send the preliminary notice on time
In most states, a subcontractor or material supplier must send a preliminary notice within a set number of days after first furnishing labor or materials. California requires it within 20 days (Civ. Code § 8800). Florida gives 45 days (§ 713.06). Texas requires monthly notices for each month worked. Missing the deadline means losing the right to lien for that period's work.
Step 3: Record the lien in the correct county
The lien is recorded with the county recorder's office in the county where the improved property sits — not where you live, not where the general contractor's office is. The recording must happen within the statutory window, which is typically measured from the date of your last day of work or from the project's completion. California: 90 days after completion (Civ. Code § 8412). Texas: the 15th day of the fourth month after the indebtedness accrues. Florida: 90 days after final furnishing (§ 713.08).
Step 4: Serve and calendar the foreclosure deadline
After recording, serve a copy of the lien on the property owner as the state requires. Then calendar the foreclosure suit deadline — the date by which you must file a lawsuit to enforce the lien or it expires. In California, you have 90 days from recording unless you record an extension (Civ. Code § 8460). In Texas, two years from the deadline to file the lien claim. Missing the foreclosure deadline turns a secured claim into an unsecured one.
Frequently asked questions
+How do I file a mechanic's lien?
Send the preliminary notice on time, record the lien in the county where the property sits within the statutory window, serve a copy on the owner, and file a foreclosure suit before the lien expires.
+Can I file a lien without a preliminary notice?
In most states, no — or at least not for the work periods the late notice would have covered. Direct contractors sometimes have an exemption, but subcontractors and suppliers almost always need the preliminary notice.
+How long does a mechanic's lien last?
It depends on the state. In California, 90 days from recording unless extended. In Texas, the lien must be foreclosed within two years. In Florida, one year from recording.
+Do I need a lawyer to file a mechanic's lien?
Not to prepare and record the lien itself. EvictFlows generates a state-compliant mechanic's lien form — free preview, court-ready PDF. A lawyer matters if the owner contests the lien or foreclosure litigation begins.