Preliminary notice before the lien clock closes

Preliminary Notice · Tex. Prop. Code ch. 53

The crew finished on May 28 and invoiced $7,400 on June 2. Texas does not measure the notice clock from the invoice: it runs off the months actually worked, which is why the paperwork started in March, not June.

Residential remodel subcontractor · 4-person crew · kitchen and two baths for a custom-home builder

What these are

These are illustrative scenarios, not customer testimonials. They are written from common workflows to show how the product behaves; they do not describe any specific customer, and they are not a promise of any outcome. EvictFlows is not a law firm and this is not legal advice.

The situation

Subcontract
$18,400
Draws received
$11,000
Unpaid at completion
$7,400
First day on site
Mar 3, 2026
Last day on site
May 28, 2026
Final invoice (not the anchor)
Jun 2, 2026

A four-person crew gutted a kitchen and two baths for a custom-home builder in Katy. Draws came in on time until the final one: $18,400 of work, $11,000 paid, $7,400 held back. The last day on site was May 28. The invoice went out June 2, and that is the date the builder's bookkeeper kept citing as the starting point for everything. It is not. Texas gives a subcontractor no lien by default — the right is built out of notices tied to the months in which labour and materials were furnished, with a separate rule for the final month of a residential job. A claimant who waits for the invoice has already missed notices for March and April, and the months it missed are the months it can no longer claim.

How the workflow runs

  1. 1

    Fix the first and last day of work

    The clock is anchored to when labour and materials were furnished, so those dates decide the notice schedule: March 3 and May 28. The form asks for them before it asks for the $7,400.

  2. 2

    Work the monthly schedule

    While the job runs, notice goes out month by month — for a month worked, on or before the 15th day of the second month after it, so March work by May 15 and April work by June 15. Residential work treats the final month under its own rule. Skipping a month does not weaken the claim proportionally; it removes the months it covered.

  3. 3

    Name the right parties

    The owner of record at the county appraisal district, the original contractor who signed the subcontract, and the statutory mailing address each have to be right. A notice that reaches the builder's holding company instead of the owner protects nothing, even when it arrives on time.

  4. 4

    Keep the proof of delivery

    Certified mail receipts and the mailing log are the evidence. The lien claim later has to show the notices went out, so the paperwork is filed with the job file, not left in a truck.

What to verify before serving

  • Notice schedule anchored to the work months, not the invoice date.
  • Residential final-month rule applied where it applies.
  • Correct owner and original contractor named.
  • Mailing receipts retained with the job file.

Where it ends up

The subcontractor sends the notices on the statutory schedule and keeps the receipts that a later lien claim has to reference.

StatuteTex. Prop. Code ch. 53State guide →