Mechanic's lien · New York City, NY

Mechanic's lien in New York City, NY

In New York City, New York, a contractor preserves a mechanic's lien with two dates: the notice of lien and its § 11 service under Lien Law § 9, then the claim of lien under Lien Law § 10. File with the county clerk within eight months of final furnishing — four months for a single-family dwelling. Service on the owner must be completed within 35 days of filing, and Lien Law § 11-bis adds a lender notice on many projects.

Governing statutes

N.Y. Lien Law § 9N.Y. Lien Law § 10N.Y. Lien Law § 17

8

months to record a claim of lien (Lien Law § 10)

1

year to sue on a recorded lien (Lien Law § 17)

$24.99

one-off, preview free

The process in New York City

  1. 1

    Serve the preliminary notice

    New York has no separate preliminary notice: the lien itself is the operative document, and it must contain the § 9 particulars before it is filed.

    Lien Law § 9

  2. 2

    Record the claim of lien

    File with the county clerk within eight months of final furnishing — four months for a single-family dwelling.

    Lien Law § 10

  3. 3

    Serve the recorded lien

    After recording, serve a copy on the owner and, where the statute requires it, on the construction lender or original contractor. Keep the receipt — service is part of perfection in most states, not an afterthought.

    Lien Law § 10

  4. 4

    Sue before the deadline

    The lien expires one year after filing unless foreclosure is commenced and a notice of pendency is filed.

    Lien Law § 17

New York City filing details

The recorder indexes a filing within days — the clock that matters is the statutory deadline, not the recorder. Confirm the current fee on the court's published schedule before you file — amounts change.

Recorded documents for New York City go to New York County Clerk — Lien Records — 60 Centre St, New York, NY 10007.

Every date on this page comes from Lien Law § 10. These deadlines are enforced strictly — a filing one day late generally leaves you with an unsecured claim instead of a lien.

Public works and bonded projects follow different statutes from private-work liens, and a payment bond usually replaces the property lien. Confirm which route the project takes before recording.

Where a lien is recorded

New York County Clerk — Lien Records

60 Centre St, New York, NY 10007

Where it is filed

Civil Court of the City of New York — Housing Court, Manhattan

111 Centre St, New York, NY 10013

Documents on this track

Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.

  • Mechanic's LienLien Law § 9
  • Notice of Intent to LienLien Law § 11
  • Lien Foreclosure NoticeLien Law § 17

Questions people ask about New York City

What happens if I miss the preliminary notice deadline?+

New York has no separate preliminary notice: the lien itself is the operative document, and it must contain the § 9 particulars before it is filed.

How long does a recorded lien stay good in New York?+

The lien expires one year after filing unless foreclosure is commenced and a notice of pendency is filed. Filing the foreclosure action and recording a lis pendens is what keeps the lien alive.

Do I need a written contract to claim a lien?+

Usually not — an oral or implied agreement can support a mechanic's lien in most states. What decides the case in practice is whether the work, price, and change orders are documented well enough to prove the unpaid balance.

Where do I file a mechanic's lien in New York City?+

With the county clerk for the county where the property sits — New York County for Manhattan. N.Y. Lien Law § 9 sets what the notice of lien must contain. A misdescribed parcel or the wrong owner can void it even if the debt is real.

When must a New York lien be filed?+

Within eight months after the claimant's final furnishing of labor or materials (Lien Law § 10). That is long by national standards, but it does not excuse waiting — the lien secures nothing until it is actually filed.

How long is a New York lien good for?+

One year from filing (Lien Law § 17). You must start the foreclosure action, or obtain a court-ordered extension, inside that year. An expired lien is void and cannot be revived by filing late.

Also in this jurisdiction: Eviction notice (New York City)

Draft your New York City lien documents now

EvictFlows drafts the preliminary notice and the claim of lien against Lien Law § 10, with the recording and suit dates printed on the document. Free preview before you pay.