Mechanic's lien · Charlotte, NC
Mechanic's lien in Charlotte, NC
In Charlotte, North Carolina, a contractor preserves a mechanic's lien with two dates: a notice of claim of lien on funds under N.C.G.S. § 44A-17, then the claim of lien under N.C.G.S. § 44A-11. File the claim of lien on real property with the clerk of superior court within 120 days after last furnishing. The property lien and the funds lien are separate instruments with separate deadlines — serving one does not preserve the other.
Governing statutes
120
days to record a claim of lien (N.C.G.S. § 44A-11)
180
days to sue on a recorded lien (N.C.G.S. § 44A-13)
$24.99
one-off, preview free
The process in Charlotte
- 1
Serve the preliminary notice
Subs and suppliers serve the notice of claim of lien upon funds on the owner and contractor to trap unpaid funds.
N.C.G.S. § 44A-17
- 2
Record the claim of lien
File the claim of lien on real property with the clerk of superior court within 120 days after last furnishing.
N.C.G.S. § 44A-11
- 3
Serve the recorded lien
After recording, serve a copy on the owner and, where the statute requires it, on the construction lender or original contractor. Keep the receipt — service is part of perfection in most states, not an afterthought.
N.C.G.S. § 44A-11
- 4
Sue before the deadline
Suit must be filed within 180 days after last furnishing — a timely filing does not extend it.
N.C.G.S. § 44A-13
Charlotte filing details
The recorder indexes a filing within days — the clock that matters is the statutory deadline, not the recorder. Confirm the current fee on the court's published schedule before you file — amounts change.
Recorded documents for Charlotte go to Mecklenburg County Clerk of Superior Court — lien filings — 832 E 4th St, Charlotte, NC 28202.
Every date on this page comes from N.C.G.S. § 44A-11. These deadlines are enforced strictly — a filing one day late generally leaves you with an unsecured claim instead of a lien.
Public works and bonded projects follow different statutes from private-work liens, and a payment bond usually replaces the property lien. Confirm which route the project takes before recording.
Where a lien is recorded
Mecklenburg County Clerk of Superior Court — lien filings
832 E 4th St, Charlotte, NC 28202
Where it is filed
Mecklenburg County District Court — small claims / summary ejectment
832 E 4th St, Charlotte, NC 28202
Documents on this track
Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.
- Preliminary NoticeN.C.G.S. § 44A-17
- Mechanic's LienN.C.G.S. § 44A-11
- Lien Foreclosure NoticeN.C.G.S. § 44A-13
Questions people ask about Charlotte
What happens if I miss the preliminary notice deadline?+
Subs and suppliers serve the notice of claim of lien upon funds on the owner and contractor to trap unpaid funds.
How long does a recorded lien stay good in North Carolina?+
Suit must be filed within 180 days after last furnishing — a timely filing does not extend it. Filing the foreclosure action and recording a lis pendens is what keeps the lien alive.
Do I need a written contract to claim a lien?+
Usually not — an oral or implied agreement can support a mechanic's lien in most states. What decides the case in practice is whether the work, price, and change orders are documented well enough to prove the unpaid balance.
What is a claim of lien on funds in North Carolina?+
N.C.G.S. § 44A-17 et seq. lets a lower-tier claimant reach money the owner still owes the contractor, separate from a lien on the property itself. It has to be served before those funds are paid out, so timing matters more than the amount.
When must the North Carolina lien be filed?+
Within 120 days after the claimant's last furnishing of labor or materials (N.C.G.S. § 44A-11). The claim is filed with the clerk of superior court in the county where the property sits, and it must state the real property and the amount claimed.
How long do I have to sue on a North Carolina lien?+
Within 180 days after the claim of lien is filed (N.C.G.S. § 44A-13). A lien that is not enforced in that window is discharged by operation of law, and unlike some states there is no routine extension to fall back on.