Mechanic's lien · Miami, FL
Mechanic's lien in Miami, FL
EvictFlows generates a FL-compliant mechanic’s lien package in minutes — free preview, statute-grounded, court-ready PDF. In Miami, Florida, a contractor preserves a mechanic's lien with two dates: a Notice to Owner under Fla. Stat. § 713.06, then the claim of lien under Fla. Stat. § 713.08. Record the Claim of Lien in the county official records within 90 days after final furnishing. Willfully exaggerated lien amounts can invalidate the lien and expose the claimant to fees, so state the unpaid amount conservatively.
Governing statutes
90
days to record a claim of lien (Fla. Stat. § 713.08)
1
year to sue on a recorded lien (Fla. Stat. § 713.22)
$24.99
one-off, preview free
The process in Miami
- 1
Serve the preliminary notice
Lienors not in privity serve the Notice to Owner before starting, or within 45 days of first furnishing; late service forfeits the lien for that work.
Fla. Stat. § 713.06
- 2
Record the claim of lien
Record the Claim of Lien in the county official records within 90 days after final furnishing.
Fla. Stat. § 713.08
- 3
Serve the recorded lien
After recording, serve a copy on the owner and, where the statute requires it, on the construction lender or original contractor. Keep the receipt — service is part of perfection in most states, not an afterthought.
Fla. Stat. § 713.08
- 4
Sue before the deadline
Suit to enforce must be filed within one year of recording — a Notice of Contest of Lien can shorten that to 60 days.
Fla. Stat. § 713.22
Miami filing details
The recorder indexes a filing within days — the clock that matters is the statutory deadline, not the recorder. Confirm the current fee on the court's published schedule before you file — amounts change.
Recorded documents for Miami go to Miami-Dade County Clerk of the Court — Official Records — Miami-Dade County, FL.
Every date on this page comes from Fla. Stat. § 713.08. These deadlines are enforced strictly — a filing one day late generally leaves you with an unsecured claim instead of a lien.
Public works and bonded projects follow different statutes from private-work liens, and a payment bond usually replaces the property lien. Confirm which route the project takes before recording.
Where a lien is recorded
Miami-Dade County Clerk of the Court — Official Records
Miami-Dade County, FL
Where it is filed
Miami-Dade County Court — Civil Division
175 NW 1st Ave, Miami, FL 33128
Documents on this track
Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.
- Preliminary NoticeFla. Stat. § 713.06
- Mechanic's LienFla. Stat. § 713.08
- Lien Foreclosure NoticeFla. Stat. § 713.22
Questions people ask about Miami
What happens if I miss the preliminary notice deadline?+
Lienors not in privity serve the Notice to Owner before starting, or within 45 days of first furnishing; late service forfeits the lien for that work.
How long does a recorded lien stay good in Florida?+
Suit to enforce must be filed within one year of recording — a Notice of Contest of Lien can shorten that to 60 days. Filing the foreclosure action and recording a lis pendens is what keeps the lien alive.
Do I need a written contract to claim a lien?+
Usually not — an oral or implied agreement can support a mechanic's lien in most states. What decides the case in practice is whether the work, price, and change orders are documented well enough to prove the unpaid balance.
What is a Notice to Owner in Florida?+
It tells the owner and the lender that a subcontractor or supplier is on the job. Fla. Stat. § 713.06 requires it within 45 days of first furnishing, and without it most claimants who did not contract with the owner lose lien rights entirely.
When must the Florida claim of lien be recorded?+
Within 90 days after the claimant's final furnishing of labor, services, or materials (Fla. Stat. § 713.08). The claim must also be served on the owner. A late or unserved claim of lien is unenforceable no matter how much is owed.
What happens if the owner contests the Florida lien?+
A notice of contest shortens your clock: you must file the foreclosure action within 60 days after service of that notice (Fla. Stat. § 713.22). Otherwise the general deadline is one year from recording. A contest can arrive long before the one-year date, so never treat that year as the real deadline.
Also in this jurisdiction: Eviction notice (Miami)
Draft your Miami lien documents now
EvictFlows drafts the preliminary notice and the claim of lien against Fla. Stat. § 713.08, with the recording and suit dates printed on the document. Free preview before you pay.