In Phoenix, Arizona, a contractor preserves a mechanic's lien with two dates: a preliminary 20-day notice under A.R.S. § 33-992.01, then the claim of lien under A.R.S. § 33-993. Record the lien claim within 120 days after completion and serve a copy on the owner — perfection needs both. A recorded notice of completion can shorten the recording window, so check the recorder's index before relying on the 120 days.
Governing statutes
120
days to record a claim of lien (A.R.S. § 33-993)
6
months to sue on a recorded lien (A.R.S. § 33-998)
$24.99
one-off, preview free
The process in Phoenix
- 1
Serve the preliminary notice
Claimants without a direct contract serve it within 20 days of first furnishing; late notice limits recovery to work done after service.
A.R.S. § 33-992.01
- 2
Record the claim of lien
Record the lien claim within 120 days after completion and serve a copy on the owner — perfection needs both.
A.R.S. § 33-993
- 3
Serve the recorded lien
After recording, serve a copy on the owner and, where the statute requires it, on the construction lender or original contractor. Keep the receipt — service is part of perfection in most states, not an afterthought.
A.R.S. § 33-993
- 4
Sue before the deadline
Foreclosure must be brought within six months after the lien is recorded.
A.R.S. § 33-998
Phoenix filing details
The recorder indexes a filing within days — the clock that matters is the statutory deadline, not the recorder. Confirm the current fee on the court's published schedule before you file — amounts change.
Recorded documents for Phoenix go to Maricopa County Recorder — 111 S 3rd Ave, Phoenix, AZ 85003.
Every date on this page comes from A.R.S. § 33-993. These deadlines are enforced strictly — a filing one day late generally leaves you with an unsecured claim instead of a lien.
Public works and bonded projects follow different statutes from private-work liens, and a payment bond usually replaces the property lien. Confirm which route the project takes before recording.
Where a lien is recorded
Maricopa County Recorder
111 S 3rd Ave, Phoenix, AZ 85003
Where it is filed
Maricopa County Justice Court — special detainer docket
Justice court precinct serving the property, Maricopa County, AZ
Documents on this track
Each one is drafted to the citations above — preview free, unlock as a court-ready PDF.
- Preliminary NoticeA.R.S. § 33-992.01
- Mechanic's LienA.R.S. § 33-993
- Lien Foreclosure NoticeA.R.S. § 33-998
Questions people ask about Phoenix
What happens if I miss the preliminary notice deadline?+
Claimants without a direct contract serve it within 20 days of first furnishing; late notice limits recovery to work done after service.
How long does a recorded lien stay good in Arizona?+
Foreclosure must be brought within six months after the lien is recorded. Filing the foreclosure action and recording a lis pendens is what keeps the lien alive.
Do I need a written contract to claim a lien?+
Usually not — an oral or implied agreement can support a mechanic's lien in most states. What decides the case in practice is whether the work, price, and change orders are documented well enough to prove the unpaid balance.
When does Arizona's 20-day preliminary notice start?+
A.R.S. § 33-992.01 requires the notice within 20 days after the claimant first furnishes labor, materials, or services. A late notice still protects later work but cuts off the earlier portion. Serve the owner and the lender — not just the general contractor.
How long do I have to record a lien in Arizona?+
Record the claim of lien with the county recorder within 120 days after the claimant's last day of work (A.R.S. § 33-993). The deadline runs from the completion of your own work, not the whole project, and the recorded claim must state a good-faith amount.
What happens after I record the Arizona lien?+
You must file the foreclosure action within six months of recording (A.R.S. § 33-998), and serve a copy of the lien on the owner. A recorded lien that is never foreclosed expires on its own. An overstated amount can be reduced or void the claim.
Also in this jurisdiction: Eviction notice (Phoenix)